Question 243 - PMP discussion
A project to build a new energy plant was just completed. However, a few days before operation of the plant, the local community protested and closed access to the plant. They argue that an important natural reserve was impacted and prior consultation was not done by the project team.
What should the project manager verify first?
A.
Stakeholder engagement plan
B.
Cost-benefit analysis
C.
Business case
D.
Risk management plan