Question 244 - PMP discussion
An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?
A.
Establish a team charter.
B.
Recognize the team's contributions.
C.
Assign a team leader.
D.
Establish a project schedule.