The project team is experiencing schedule delays due to issues arising with suppliers. Some of the tasks are on the critical path.

What should the project manager do in this situation?

A.
Discuss the critical path issues with the purchasing department.
Answers
A.
Discuss the critical path issues with the purchasing department.
B.
Review the critical path with the stakeholders to define next steps.
Answers
B.
Review the critical path with the stakeholders to define next steps.
C.
Review the work breakdown structure (WBS) with the suppliers.
Answers
C.
Review the work breakdown structure (WBS) with the suppliers.
D.
Escalate the supplier-related issues to the sponsor for resolution.
Answers
D.
Escalate the supplier-related issues to the sponsor for resolution.
Suggested answer: A