Question 252 - PMP discussion
In a daily standup meeting, a project manager notices that a team member's reports include incomplete tasks with no impediments. A colleague informs the project manager that this team member is experiencing a personal issue.
What should the project manager do?
A.
Ask the human resources (HR) manager to speak with this team member.
B.
Coach the team member on how to keep work and personal issues separate.
C.
Reallocate this team member's tasks to others for the immediate future.
D.
Understand the team member's personal issue and offer them support.
Your answer: