Question 258 - PMP discussion

Report
Export

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?

A.
Consult the risk response plan.
Answers
A.
Consult the risk response plan.
B.
Update the resource calendar.
Answers
B.
Update the resource calendar.
C.
Issue a request to the change control board (CCB).
Answers
C.
Issue a request to the change control board (CCB).
D.
Assign the tasks to another team member.
Answers
D.
Assign the tasks to another team member.
Suggested answer: B