In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.
What should the project manager do?
A.
Consult the risk response plan.
B.
Update the resource calendar.
C.
Issue a request to the change control board (CCB).
D.
Assign the tasks to another team member.