Question 259 - PMP discussion
A project manager notices a conflict in the team on both technical and interpersonal levels during the execution phase of a project.
What should the project manager do?
A.
Hold a team meeting to understand and address the conflict.
B.
Schedule a monthly meeting to handle all project conflicts.
C.
Address the conflicts during the lessons learned session.
D.
Hire an external consultant to lead an organizational intervention.
Your answer: