A project manager discovers that the project team is spending a large amount of time delivering several reporting formats for the same project updates to multiple stakeholders.

What should the project manager do to reduce the time spent on these activities?

A.
Update the communications management plan to remove less influential stakeholders.
Answers
A.
Update the communications management plan to remove less influential stakeholders.
B.
Delegate all of the stakeholder communications activities to a project team member.
Answers
B.
Delegate all of the stakeholder communications activities to a project team member.
C.
Segment the types of communications to be delivered to different stakeholders.
Answers
C.
Segment the types of communications to be delivered to different stakeholders.
D.
Hold biweekly status meetings to deliver information to all stakeholders at once.
Answers
D.
Hold biweekly status meetings to deliver information to all stakeholders at once.
Suggested answer: C