Question 263 - PMP discussion
When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined.
What should the project manager do?
A.
Forward the issue to the benefit owner and ask them to collect the missing data and build the KPIs.
B.
Coordinate with the benefit owner to track and collect the missing data and build the KPIs.
C.
Work with the business analysts to track and collect the missing data and build the KPIs.
D.
Ask the program manager to track and collect the missing data and work to build the KPIs.