ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 269 - PMP discussion

Report
Export

A project manager has been asked to participate in the procurement process for a software application that allows customers to buy online e-learning courses.

The project manager will take over the project once the supplier has been sourced.

What should the project manager do before the project starts?

A.
Ask the project sponsor to involve the legal department in the negotiation for the project agreement.
Answers
A.
Ask the project sponsor to involve the legal department in the negotiation for the project agreement.
B.
Notify the project sponsor that the project manager cannot be involved in the agreement negotiation process.
Answers
B.
Notify the project sponsor that the project manager cannot be involved in the agreement negotiation process.
C.
Inform the project sponsor that once the agreement has been signed, there cannot be any changes to the scope of the project.
Answers
C.
Inform the project sponsor that once the agreement has been signed, there cannot be any changes to the scope of the project.
D.
Ensure that the requirements for the project are understood and that the objectives are verified before approval of an agreement.
Answers
D.
Ensure that the requirements for the project are understood and that the objectives are verified before approval of an agreement.
Suggested answer: A
asked 23/09/2024
mr Craig Ferguson
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first