During project implementation, one team finds out that a key project deliverable was not budgeted.

What should the project manager do first?

A.
Escalate the issue to the project sponsor for resolution.
Answers
A.
Escalate the issue to the project sponsor for resolution.
B.
Hold the team accountable and ask for an immediate solution.
Answers
B.
Hold the team accountable and ask for an immediate solution.
C.
Meet with the team to discuss alternatives.
Answers
C.
Meet with the team to discuss alternatives.
D.
Remove the deliverable from the project scope.
Answers
D.
Remove the deliverable from the project scope.
Suggested answer: C