Question 272 - PMP discussion
During the final stage of the launch for a new design, team members are having a conflict about some features of the design.
What should the project manager do?
A.
Call a stakeholder meeting along with team members and seek consensus.
B.
Ask stakeholders to reduce the scope in order to meet project deadlines.
C.
Ask the project sponsor to make the decision about the design features.
D.
Review the design with the team members and propose a new launch date.
Your answer: