From previous lessons learned working with a client, a project manager notes that the client's turn-around times on documents sent for approval were very slow and well outside of the agreed timelines.
At the initial kick-off meeting with the same client, how should the project manager approach this issue for the new project?
A.
Update the project risk register with the potential for delays.
B.
Inform the client that extra resources will be added to give the client more time for reviews.
C.
Work with the client on an acceptable amount of time for document approval.
D.
Inform the client of their responsibility in relation to document approval.