Question 293 - PMP discussion

Report
Export

During an ongoing project, a key resource asks the project manager about the project purpose and if it is aligned with the organization's strategy.

What should the project manager share with the key resource?

A.
The updated project management plan
Answers
A.
The updated project management plan
B.
The updated benefits management plan
Answers
B.
The updated benefits management plan
C.
The updated communications management plan
Answers
C.
The updated communications management plan
D.
The updated scope management plan
Answers
D.
The updated scope management plan
Suggested answer: B