Question 294 - PMP discussion

Report
Export

After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run.

What two actions should the project manager take? (Choose two.)

A.
Send a questionnaire to the project participants and seek their feedback.
Answers
A.
Send a questionnaire to the project participants and seek their feedback.
B.
Refer to the communications management plan.
Answers
B.
Refer to the communications management plan.
C.
Obtain official approval on the new process from the various countries.
Answers
C.
Obtain official approval on the new process from the various countries.
D.
Prepare the lessons learned from the project phase.
Answers
D.
Prepare the lessons learned from the project phase.
E.
Deliver the project materials to the users and see if they have any comments.
Answers
E.
Deliver the project materials to the users and see if they have any comments.
Suggested answer: A, B