A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client. A potential design problem is identified by the development team. After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed. The design is already approved.

What should be the project manager's next steps?

A.
Make a change request and get formal approval from the project owner.
Answers
A.
Make a change request and get formal approval from the project owner.
B.
Inform the client of the problem and follow the change request process.
Answers
B.
Inform the client of the problem and follow the change request process.
C.
Conduct a proof of concept to make sure there are no problems in the revised design.
Answers
C.
Conduct a proof of concept to make sure there are no problems in the revised design.
D.
Amend the design specifications and pass them to the development team for reprogramming.
Answers
D.
Amend the design specifications and pass them to the development team for reprogramming.
Suggested answer: C