During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams.

As a team facilitator, what should the project manager do to avoid this?

A.
Reunite with the project team members affected and tell them not to reduce the team's capacity.
Answers
A.
Reunite with the project team members affected and tell them not to reduce the team's capacity.
B.
Hire a coach to help all project teams to improve their abilities to solve problems on their own.
Answers
B.
Hire a coach to help all project teams to improve their abilities to solve problems on their own.
C.
Recommend to the project team members that they should improve their planning and make their stories smaller.
Answers
C.
Recommend to the project team members that they should improve their planning and make their stories smaller.
D.
Identify the problem's root causes and define the ground rules with all project team members to minimize interferences.
Answers
D.
Identify the problem's root causes and define the ground rules with all project team members to minimize interferences.
Suggested answer: D