List of questions
Related questions
Question 303 - PMP discussion
A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25%. The project manager updated the risk register and kept the project running as normal. The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.
What should the project manager have done to avoid this?
A.
Implemented the communications management plan properly.
B.
Implemented the stakeholder engagement plan correctly.
C.
Provided a proper risk response.
D.
Ensured the risk tolerance of the company was properly updated.
Your answer:
0 comments
Sorted by
Leave a comment first