A company is changing their current business model. The change requires implementing a complex project using multiple agile teams.

What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three.)

A.
Story testing
Answers
A.
Story testing
B.
Tests based on behavior and test-driven development
Answers
B.
Tests based on behavior and test-driven development
C.
Independent personal testing
Answers
C.
Independent personal testing
D.
Security and performance testing
Answers
D.
Security and performance testing
E.
An experimental approach to cover all possible choices
Answers
E.
An experimental approach to cover all possible choices
Suggested answer: A, B, D