Question 306 - PMP discussion
A new resource has joined an iterative project team. The project manager notices that the resource is unable to complete the deliverables on time.
How should the project manager address this situation?
A.
Discuss options to improve performance with the resource manager.
B.
Provide performance feedback as part of the retrospective ceremony.
C.
Address the lack of performance by coaching the new team member.
D.
Request a more efficient replacement resource from the project sponsor.