A large corporation is transforming itself from a predictive to agile approach. A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.

How should these conflicts be resolved?

A.
Train the executives on agile practices.
Answers
A.
Train the executives on agile practices.
B.
Include the executives in team retrospectives.
Answers
B.
Include the executives in team retrospectives.
C.
Negotiate with the executives and agree on a process.
Answers
C.
Negotiate with the executives and agree on a process.
D.
Request that the executives use agile practices.
Answers
D.
Request that the executives use agile practices.
Suggested answer: A