Question 308 - PMP discussion
A transportation company is transforming its operational processes and the main system this company uses to move freight. The scope statement is in place. An iterative delivery approach has been agreed by all stakeholders.
What does the project manager need to do next to help the team understand the work that needs to be done?
A.
Create the requirements management plan to outline how project requirements will be collected, analyzed, and documented, and then assign requirements to team members.
B.
Work with the team to decompose the scope into a WBS and work packages in order to create required deliverables and timelines.
C.
Start working on the project management plan with work packages, a detailed schedule, and work assignments for team members.
D.
Work directly with stakeholders on the work breakdown structure (WBS) and assign tasks with a required timeline for each team member to start the work.