ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 312 - PMP discussion

Report
Export

A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low- level risks remain.

What should the project manager do now?

A.
Reclassify low-level risks as high-level risks.
Answers
A.
Reclassify low-level risks as high-level risks.
B.
Notify stakeholders that all high-level risks have been resolved.
Answers
B.
Notify stakeholders that all high-level risks have been resolved.
C.
Reduce the priority of project risks as all remaining risks are low-level.
Answers
C.
Reduce the priority of project risks as all remaining risks are low-level.
D.
Reevaluate identified risks and update the risk register.
Answers
D.
Reevaluate identified risks and update the risk register.
Suggested answer: D
asked 23/09/2024
Nikki Matheson
32 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first