Question 312 - PMP discussion
A project manager is leading a project that is in an advanced stage. All high-level risks identified in the risk management plan have been resolved or are no longer a risk for the project. Only low- level risks remain.
What should the project manager do now?
A.
Reclassify low-level risks as high-level risks.
B.
Notify stakeholders that all high-level risks have been resolved.
C.
Reduce the priority of project risks as all remaining risks are low-level.
D.
Reevaluate identified risks and update the risk register.