ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 313 - PMP discussion

Report
Export

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond?

A.
Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.
Answers
A.
Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.
B.
Explain to the stakeholder that the stakeholder engagement plan requires their attendance at all reviews.
Answers
B.
Explain to the stakeholder that the stakeholder engagement plan requires their attendance at all reviews.
C.
Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework.
Answers
C.
Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework.
D.
Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance.
Answers
D.
Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance.
Suggested answer: C
asked 23/09/2024
Fthcx Fgghn
33 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first