Question 314 - PMP discussion
The product team is progressing with a prototyping approach to deliver a multiyear business initiative. A few user stories are taking longer to be delivered.
What should the project manager do?
A.
Determine the risks and identify a resolution during the retrospective meeting.
B.
Inform stakeholders about the delay during project updates.
C.
Discover the gaps in the communications management plan and address them accordingly.
D.
Determine cross-dependencies and plan a spike in the next sprint.