A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources.

What should the project manager do next?

A.
Review the risk management plan to identify the response strategy.
Answers
A.
Review the risk management plan to identify the response strategy.
B.
Escalate the issue to the sponsor and debrief them about the situation.
Answers
B.
Escalate the issue to the sponsor and debrief them about the situation.
C.
Review the milestone list to determine which tasks can be fast-tracked.
Answers
C.
Review the milestone list to determine which tasks can be fast-tracked.
D.
Organize a team meeting to discuss the next course of action.
Answers
D.
Organize a team meeting to discuss the next course of action.
Suggested answer: D