A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results.

Which tool or technique should the project manager use?

A.
Change control tools
Answers
A.
Change control tools
B.
Expert judgment
Answers
B.
Expert judgment
C.
Autocratic decision making
Answers
C.
Autocratic decision making
D.
Context diagram
Answers
D.
Context diagram
Suggested answer: A