A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project.

What should the project manager do to enhance the success of the project?

A.
Schedule a meeting with the new stakeholder.
Answers
A.
Schedule a meeting with the new stakeholder.
B.
Share the project status reports with the new stakeholder.
Answers
B.
Share the project status reports with the new stakeholder.
C.
Update the stakeholder engagement plan.
Answers
C.
Update the stakeholder engagement plan.
D.
Add the new stakeholder to the communications management plan.
Answers
D.
Add the new stakeholder to the communications management plan.
Suggested answer: A