During the course of the project, several obstacles are identified that are preventing the project from moving forward.
What should the project manager do to remove the obstacles?
A.
Have the project team work on other activities
B.
Implement plans to remove the obstacles
C.
Escalate to the project steering committee
D.
Prioritize the obstacles for resolution
Your answer: