List of questions
Related questions
Question 330 - PMP discussion
A project manager is working with a Scrum team that is continually missing deadlines. The steering committee is concerned about the project as it is not clear that it will deliver the expected value. After some analysis, the project manager discovers there is a mismatch of competencies in one of the teams.
What should the project manager do?
A.
Emphasize to the teams the importance of meeting the agreed deadlines
B.
Provide appropriate training to compensate for the mismatch
C.
Update the project schedule to reflect the delay
D.
Accept the risk of the project missing deadlines due to the mismatch
Your answer:
0 comments
Sorted by
Leave a comment first