The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project.
What tools can be used to provide this information?
A.
A release burndown chart
B.
Analysis of the business requirements document
C.
Story points for the remaining user stories
D.
Surrogate measurements