The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project.

What tools can be used to provide this information?

A.
A release burndown chart
Answers
A.
A release burndown chart
B.
Analysis of the business requirements document
Answers
B.
Analysis of the business requirements document
C.
Story points for the remaining user stories
Answers
C.
Story points for the remaining user stories
D.
Surrogate measurements
Answers
D.
Surrogate measurements
Suggested answer: A