ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 348 - PMP discussion

Report
Export

The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept this rejection and does not want to continue the project without the change.

What should the project manager have done to avoid this situation?

A.
Requested that the sponsor approved the change request first
Answers
A.
Requested that the sponsor approved the change request first
B.
Assessed the change's overall impact to the project before submission
Answers
B.
Assessed the change's overall impact to the project before submission
C.
Ensured that the change request was aligned with the project scope
Answers
C.
Ensured that the change request was aligned with the project scope
D.
Submitted the change request directly to the CCB
Answers
D.
Submitted the change request directly to the CCB
Suggested answer: B
asked 23/09/2024
Yohan Frachisse
35 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first