The change control board (CCB) rejects a change request submitted by a subject matter expert (SME). The SME refuses to accept this rejection and does not want to continue the project without the change.
What should the project manager have done to avoid this situation?
A.
Requested that the sponsor approved the change request first
B.
Assessed the change's overall impact to the project before submission
C.
Ensured that the change request was aligned with the project scope
D.
Submitted the change request directly to the CCB