A food company is developing a new product using a predictive approach, and the product is currently in the testing phase. Given the nature of the feedback of the tests, the project manager has decided to use an iterative approach. At the end of one of the iterations, a new regulation related to the product is enacted.
What should the project manager do next?
A.
Make a change request regarding the project's scope to ensure compliance
B.
Include an assessment to verify compliance in the next iteration
C.
Conduct an iteration review to address the new regulation
D.
Start the tests over, adapting the trials to the new regulation