A project manager is managing an innovation project for a big corporation. The project manager is planning to use email as the main communication channel; however, the product owner prefers to use another approved communication tool instead of email.

What should the project manager do?

A.
Contact the sponsor to request direction regarding the communication tool to be used by the project team
Answers
A.
Contact the sponsor to request direction regarding the communication tool to be used by the project team
B.
Update the communications management plan based on the product owner's preferences and distribute to the team
Answers
B.
Update the communications management plan based on the product owner's preferences and distribute to the team
C.
Suggest to the team to start using the communication tool suggested by the product owner
Answers
C.
Suggest to the team to start using the communication tool suggested by the product owner
D.
Request the product owner to use email because using another tool will increase the workload
Answers
D.
Request the product owner to use email because using another tool will increase the workload
Suggested answer: B