A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments.

What should the project manager suggest that the product owner do next?

A.
Ensure that the impediments are captured and prioritized based upon the highest valued features
Answers
A.
Ensure that the impediments are captured and prioritized based upon the highest valued features
B.
Estimate the financial impact of the impediments and request additional funding
Answers
B.
Estimate the financial impact of the impediments and request additional funding
C.
Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment
Answers
C.
Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment
D.
Capture the impediments and inform management that their assistance is needed in resolving the impediments
Answers
D.
Capture the impediments and inform management that their assistance is needed in resolving the impediments
Suggested answer: A