Question 360 - PMP discussion
A project manager is leading an in-house company project in its very early stages. This current project is similar to another project that ended a year ago.
What should the project manager do to analyze the involved stakeholders?
A.
Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project
B.
Use lessons learned from the previous project as a guide for the current project's stakeholder register
C.
Refer to the stakeholder register from the previous project as it was similar to the current project
D.
Document in the risk register that the current project may have different stakeholders than the previous project
Your answer: