A client is structured as a matrix organization for an agile project. The project manager is working on-site with key stakeholders from different parts of the organization.
How should the project manager handle the different stakeholders?
A.
All stakeholders are important, so the project manager should follow directions provided by management and key stakeholders
B.
Because there are different perspectives, perform a stakeholder analysis and act based on the outcome
C.
The project manager is working on the client's premises, so follow the directions of all the key stakeholders
D.
This is an agile project, so listen only to the directions of the project manager's supervisor and the functional managers of the organization