A member of the board of directors is the sponsor of a project that is important to the organization. This stakeholder has many other priorities and is not currently engaged in the project activities.

How should the stakeholder be engaged in the project?

A.
Keep the stakeholder informed and consult with them based on their needs
Answers
A.
Keep the stakeholder informed and consult with them based on their needs
B.
Involve the stakeholder in governance and decision making
Answers
B.
Involve the stakeholder in governance and decision making
C.
Consult with the stakeholder and increase their level of interest
Answers
C.
Consult with the stakeholder and increase their level of interest
D.
The stakeholder needs to be made aware of the project progress
Answers
D.
The stakeholder needs to be made aware of the project progress
Suggested answer: A

Explanation:

Keep the stakeholder informed and consult with them based on their needs is the best approach.

This will ensure that the stakeholder is kept up to date on the project's progress and can provide input or guidance when necessary. It is important to consult with the stakeholder to understand their needs and priorities and to align the project with those as much as possible.