A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders. The project manager has been assigned and is now in the project planning phase.

What item(s) should the project manager develop first?

A.
A product backlog and identification of the features to be delivered
Answers
A.
A product backlog and identification of the features to be delivered
B.
A business case and scope document
Answers
B.
A business case and scope document
C.
A communications management plan that addresses the team's needs
Answers
C.
A communications management plan that addresses the team's needs
D.
A risk management plan to incorporate known risks
Answers
D.
A risk management plan to incorporate known risks
Suggested answer: C