The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details.

What should be the priority order in the product backlog?

A.
Risk 3, Risk 1, Risk 2, Requirement 3, Requirement 1, Requirement 2
Answers
A.
Risk 3, Risk 1, Risk 2, Requirement 3, Requirement 1, Requirement 2
B.
Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2
Answers
B.
Requirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2
C.
Requirement 3, Requirement 1, Requirement 2
Answers
C.
Requirement 3, Requirement 1, Requirement 2
D.
Requirement 3, Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2
Answers
D.
Requirement 3, Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2
Suggested answer: D