Question 385 - PMP discussion
One of the main inputs required for a deliverable is missing due to a miscommunication between the vendor and project manager. Because of the missed deliverable, the critical path of the project is extended.
What should the project manager do next?
A.
Start an audit of the vendor's processes and procedures
B.
Review lessons learned from previous projects with this vendor
C.
Make a detailed analysis on vendor issues during the project
D.
Execute a contingency plan to address the issue with the vendor
Your answer: