A new project manager is planning an information security project for a company that resides in different countries.
What is the first step the project manager should take to gather customer requirements?
A.
Conduct a stakeholder analysis to identify how regional policies may influence needs
B.
Request relevant stakeholders to conduct an analysis and reach consensus independently
C.
Conduct a project scope review workshop with relevant stakeholders
D.
Conduct project planning meetings in one location with relevant stakeholders