A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project. This is not the first time the request has been made and the previous project failed when adaptive tools were implemented.

What should the project manager do?

A.
Prepare a change request and seek approval from the steering committee regarding the new project framework
Answers
A.
Prepare a change request and seek approval from the steering committee regarding the new project framework
B.
Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan
Answers
B.
Conduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan
C.
Bring in a third party company to develop and implement a hybrid framework for this specific project
Answers
C.
Bring in a third party company to develop and implement a hybrid framework for this specific project
D.
Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects
Answers
D.
Recommend to the PMO that it is not the right time to start implementing adaptive tools in projects
Suggested answer: C