ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 389 - PMP discussion

Report
Export

To estimate the costs of a new project that is similar to a project that was implemented last year, the project manager meets with a group of experts from the previous project. The group uses a three-point estimating technique. The project manager submits the estimated budget to the project sponsor for approval. The project sponsor, who is new to the company, is concerned because the budget exceeded their expectations.

What should the project manager do?

A.
Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate
Answers
A.
Review the organizational process assessment to determine if a contingency reserve was considered in the budget estimate
B.
Review the historical information and lessons learned from last year's project to justify the new budget estimate
Answers
B.
Review the historical information and lessons learned from last year's project to justify the new budget estimate
C.
Change the budgeting technique to a more accurate, bottom-up cost estimation
Answers
C.
Change the budgeting technique to a more accurate, bottom-up cost estimation
D.
Use soft skills to convince the project sponsor to approve the new budget estimate
Answers
D.
Use soft skills to convince the project sponsor to approve the new budget estimate
Suggested answer: B
asked 23/09/2024
Mareah Allawi
31 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first