Question 390 - PMP discussion

Report
Export

The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders. This issue is putting the project schedule at risk.

What should the project manager do first to facilitate the approval of project requirements'?

A.
Review the project charter
Answers
A.
Review the project charter
B.
Perform a stakeholder analysis
Answers
B.
Perform a stakeholder analysis
C.
Identify the source of the disagreement
Answers
C.
Identify the source of the disagreement
D.
Hold a team-building event
Answers
D.
Hold a team-building event
Suggested answer: C