List of questions
Related questions
Question 407 - PMP discussion
During project execution, the project manager discovered that a key deliverable was missing from the scope of work. After investigation, the project manager and the team discovered that the missing deliverable will impact the critical path.
What should the project manager do to avoid future delays?
A.
Submit a change request.
B.
Add additional resources to the project
C.
Update the scope of work
D.
Review the risk management plan
Your answer:
0 comments
Sorted by
Leave a comment first