ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 408 - PMP discussion

Report
Export

During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43 What should the project manager do?

A.
Ask the project team to perform the modifications since the project budget and schedule can support them.
Answers
A.
Ask the project team to perform the modifications since the project budget and schedule can support them.
B.
Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested.
Answers
B.
Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested.
C.
Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.
Answers
C.
Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.
D.
Analyze the reason for the gap in understanding with both sides and negotiate a solution.
Answers
D.
Analyze the reason for the gap in understanding with both sides and negotiate a solution.
Suggested answer: D
asked 23/09/2024
carlos soto
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first