Question 409 - PMP discussion
Some members of a project team are frustrated by a new team member who previously worked in a Scrum setting. This new team member approaches members of the project team on a daily basis in what appears to be an attempt to engage in individual standup meetings.
What should the project manager do?
A.
Schedule a meeting for the project team to review the communications management plan.
B.
Tell the rest of the project team to continue discussions with the new team member.
C.
Send an email to the project team outlining the communications strategy.
D.
Mentor the new team member on the methodology the project team is using.