Question 412 - PMP discussion

Report
Export

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan. The project team evaluated the product's feasibility of functionality and accelerated testing.

What should the project manager do as a servant leader?

A.
Support the team as necessary to find the minimum viable product (MVP).
Answers
A.
Support the team as necessary to find the minimum viable product (MVP).
B.
Amend the project budget to include MVP testing.
Answers
B.
Amend the project budget to include MVP testing.
C.
Submit a change request to the project sponsor for accelerated testing.
Answers
C.
Submit a change request to the project sponsor for accelerated testing.
D.
Develop the product as per the schedule to perform integration and testing.
Answers
D.
Develop the product as per the schedule to perform integration and testing.
Suggested answer: A
asked 23/09/2024
Timo Fahlenbck
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first