ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 413 - PMP discussion

Report
Export

The project charter was just approved and the project sponsor has given permission to proceed with the project. The program manager has confirmed that one of the requested key resources is also needed on another project at the same time. This will affect project delivery.

What should the project manager do?

A.
Pay overtime to key resource to get the work done outside of working hours
Answers
A.
Pay overtime to key resource to get the work done outside of working hours
B.
Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects
Answers
B.
Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects
C.
Speak with the client to see if the project delivery deadline can be delayed due to resource availability
Answers
C.
Speak with the client to see if the project delivery deadline can be delayed due to resource availability
D.
Talk to the program manager and about prioritizing this project over other projects so the key resources are available
Answers
D.
Talk to the program manager and about prioritizing this project over other projects so the key resources are available
Suggested answer: B
asked 23/09/2024
Francisco Rocha de Oliveira Junior
28 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first