A company has decided to implement a new archiving system. A data breach occurred during the implementation of the project.

What should the project manager do first?

A.
Implement the planned risk response to handle the issue
Answers
A.
Implement the planned risk response to handle the issue
B.
Review possible alternative documentation methods with team
Answers
B.
Review possible alternative documentation methods with team
C.
Update the risk register with the risk and proposed impact
Answers
C.
Update the risk register with the risk and proposed impact
D.
Ask the team to fix the system to resolve the issue
Answers
D.
Ask the team to fix the system to resolve the issue
Suggested answer: A

Explanation:

You could ask the team to fix it first, however that might not be the FIRST thing you have to do.

You may have to notify supervisors/security, notify customers, work with authorities of some kind, there's plenty of things that will likely be in the risk response before asking the team to fix it.

Explanation: